text.skipToContent text.skipToNavigation


​​​​​​​Dycore takes lighting to the next level

Improved visibility enhances safety and work comfort

Precast concrete flooring systems for residential and non-residential construction. At Dycore they know all about it. Adequate lighting in both production and transferring of these floors is essential. Safety comes first, closely followed by the avoidance of damage.

Jos de Laat, head of the Technical Department at Dycore Breda, explains that as a specialist they like to focus exclusively on concrete floors, with other affairs being regularly outsourced. “For our lighting, I rely on itsme’s specialism.”

“Here in Breda, we have a team of 45 people working on wide slab floors. These semi-finished products consist of a concrete shell with reinforcement. It’s not until the slabs are in place at the construction site that a concrete end layer is poured onto them”, Jos explains. Note: we are talking concrete floor parts here of 10 x 3 metres and a height of up to 30 centimetres. 

It requires a gigantic 30-ton fork lift to relocate these concrete slabs to the stacking field, where all products are awaiting transport. The slabs are accurately positioned on truck trailers, obviously without hitting anything. Moreover, the stacking field can be quite hectic with heavy transport coming and going and people walking around the vehicles. This makes good visibility essential. During daytime, things worked out fine but when darkness fell, it all became a different story. 

 

A lighting solution for every application

Around that same period, itsme installed a number of test fixtures in the Dycore production hall because the lighting there also required renewal. Jan Straetemans, lighting specialist itsme, advised to double the lighting level from 25 to 50 lux, based on a lighting plan. For the technical workshop he even recommended 500 lux, suiting the fine-mechanical work which involves small bearings and screws. It was also Jan who suggested the use of lamps with a colour temperature of 5000 K. “It’s whiter and it’s closer to natural daylight. We tested several wattages and it actually did turn out to be more comfortable to work with”, says Jos. 

“For our lighting, I rely on itsme’s specialism”

And so, it didn’t take much to convince Jos when Han Elsen, account manager at itsme, suggested to involve itsme Lighting Technology in the stacking field lighting project. Jos: “The indoor lighting project was running smoothly so I was pretty confident that this would also turn out fine.”

The outdoor area, however, posed an extra challenge. “Supplying the materials is one thing”, Han says. “You’re also facing a complete infrastructure though: the wiring and all the cabinets that need to be installed inside the lighting masts. We don’t have that expertise available ourselves.” For Dycore, however, it would mean a major advantage to keep everything central with one company taking on the entire project.  Jos: “If you are working on a project with several companies, something is always bound to fall between the cracks. I prefer working with a single party.” That is why itsme appealed to their own network, ending up at Hans Eek Infrawerken from Rossum.


They had collaborated with this customer before and, more importantly, they were one of the few parties having experience with the exceptionally high masts of 18 metres, where 10 to 12 metres is pretty much the standard.  
 

“It’s like working in daylight”

Dycore asked itsme to provide the entire stacking field with a lighting level of 50 lux, in line with the standard that applies to the kind of work which is being carried out there. Jan designed a lighting plan for that purpose, mapping out all light points in 3D. By moving, adding or removing them, he calculated the effects of certain investments. Colours graphically indicated the minimum and maximum lighting level. They also showed how to achieve an optimal light output at the lowest possible costs. This resulted in 11 new led fixtures with asymmetrical light distribution. 

 

Team efforts

​​​​​​​After Hans Eek Infrawerken had attached the fixtures to the masts, they had to adjust the fixtures. 
Normally, this is done by testing on-site. However, given the fact that Jan was familiar with all lamp specifications and had also calculated the effects in his lighting plan, he was able to provide instant, specific advice. To set the fixtures slightly flatter, for instance, preventing the light from shining in people’s eyes. Or to tilt them at a certain angle, creating an optimal light distribution on the floor. An additional service to Dycore for which he gladly returned. Jan says enthusiastically: “When the fixtures are being installed, there’s actually nothing much I can do. But I find it super interesting to come and see and assist Hans Eek in aligning those fixtures. This way, we as itsme, stay closely involved in the project.”

“Afterwards, I spoke to an employee working on the stacking field”, Han says. “He told me that the situation improved tremendously in terms of safety and work pleasure. You no longer have to be afraid of tripping over something in the dark, you can read all the labels on the floor slabs without secondary lighting.” The new lighting didn’t go entirely unnoticed in the surrounding area either. Jos laughs: “People sometimes joke that we moved the Breda football stadium to the Dycore stacking field. It really is a massive light source, it’s almost like working in daylight.” 

​​​​​​​

Long lifecycle with led

Dycore is part of Irish company CRH, which is globally represented by 79,000 employees, mainly in the construction industry. Dycore first established itself in Oosterhout, followed by branches in Lelystad and Breda; at each location specific types of concrete floors are manufactured. Their history goes back to 1975. Back in those days, with gas-discharge lamps still being mainstream, light intensity started to decrease after 4 years. For the illumination of the stacking field, Dycore opted for Philips led fixtures. The project concerned 4 new light masts with a height of 18 metres, containing 2 led fixtures of 1314 watts each. 2 existing masts, measuring 18 metres as well, were provided with a total of 3 led fixtures of 1314 watts. All in all, it would involve quite a job to replace all lamps. However, based on 3600 burning hours annually, replacement doesn’t have to be scheduled within the coming 30 to 40 years.
 

Check out our other success stories:

  • TESTIMONIAL
    15 feb. 2024
    Enduro - Complete package for heavy-duty work
    Enduro Softslings builds machines for the manufacture of its own heavy lifting soft slings. For a new machine, it called in itsme for the full package: advice on the drives, supply of components and programming of the controls. “We completed the entire project in just over six months. That’s fast for such a specialised machine.”
    Read more
  • TESTIMONIAL
    29 nov. 2023
    Azteq - Warm Cooperation on Solar Thermal Energy
    Azteq aims to revolutionise European green heat technologies on an industrial scale and is developing solar heating systems to do so. The Belgian start-up cooperates in projects with technical service providers, who in turn call upon Breemes for advice and the supply of components. For a major project in Seville, there were challenges regarding the delivery times of the decentralised PLCs and on how they could communicate with each other in the large facility.
    Read more
  • TESTIMONIAL
    22 nov. 2023
    BMI - Providing Peace of Mind by Mapping Drives
    At RBB, the production of concrete roof tiles runs on drives that mostly come from Danfoss and are up to 20 years old. Breemes assessed their status and made recommendations for maintenance, replacement and standardisation. As a result, the supplier provided its customer RBB with higher efficiency in terms of spare stocks of drives and energy consumption in production - and ultimately a better night's sleep.
    Read more
  • TESTIMONIAL
    15 nov. 2023
    Vicoma - Virtual Reality Actually Delivers Lighting Benefits
    A lighting plan may look nice on paper or screen, but ultimately what counts is what the lighting does in reality. Virtual reality can help to get a good idea of this in advance. Consultant Vicoma and lighting expert itsme proved it in a project for the Royal Netherlands Navy. "They knew within 7 minutes: ‘That’s how we want it’."
    Read more

Stay up to date with the latest news:

  • NEWS
    21 mrt. 2024
    Phoenix Contact - HEAVYCON
    With HEAVYCON Click-in, contact blocks mount easily, reliably and without tools in EVO and STANDARD connector housings. The audible and tangible "click" confirms the quick installation.
    Read more
  • NEWS
    18 mrt. 2024
    Murr - Compact Control and Signaling Modules
    Compact, flexible and easy to install - this is how the new compact control and signaling modules can be described, with which Murrelektronik expands its range of pushbuttons with standard M12 connection for electrical installations.
    Read more
  • NEWS
    13 mrt. 2024
    Wago - Collect energy data with WAGO Power Quality and MID modules
    Learn more about WAGO's Power Quality and MID modules. These modules offer manufacturers accurate measurements and in-depth analysis of power, providing a solid foundation for predictive maintenance systems that can identify failures even before they occur.
    Read more
  • NEWS
    7 mrt. 2024
    ABB - The next generation of industrial modular circuit breakers
    Discover a new level of performance, efficiency and safety with the S300P industrial modular circuit breakers. The series replaces the existing S200P series and offers numerous new features. The S300P provides reliable protection in demanding applications in industrial plants, heavy duty OEM, marine, data centres, battery charging systems. With a high short-circuit resistance of 25 kA over the entire series (0.2 A-63 A), safety is improved and downtime reduced.
    Read more

Take a look at these promotions:

Why not take a look at these trainings we offer: